Modules are assembled

After only two work sessions we have all the modules assembled (frames).

Module assembly

Today, Davor and Boki continued where we last left off and assembled remaining  modules.
Two angled pieces for corner modules is all that is left after todays work. They are designed so they are not part of the framework structure but serve just as part of a fascia.
To get the idea how big it will be we put all the frames on the garage floor. We had to separate everything in two part because it was to long for garage. Missing are the 2 station modules from last time and barge segment which runs parallel to those new modules.

First Roadbed

Finally, for the end of the day we glued cork to subroadbed on one simple module and fixed it to the module. Sure, it was the simple module but it was a milestone whatsoever.