Plastering of a Mine module

Work on Davors Mine module is progressing. We finished shaping foam on it. Only part left unfinished is area where the future mine building will be.


Since we are not sure about the choice of building we decided to leave that area empty and finish it later when the concept of mine itself will be decided.

All the tracks were covered with painters tape to protect them from plaster. Plastering was done with combination of thick and thin mixture of plaster depending on the shape.

After plastering, everything was dusted with thin layer of plaster dust. Rock castings were cleaned and plaster was sprayed with water to harden.
This gives some rougher texture and cover un-natural formations.